Countries · Malaysia国家地区 · 马来西亚
Where can AI data centres be built in Malaysia, and how do power, water and a tropical climate shape the cooling?马来西亚哪里建得起 AI 数据中心?电、水和热带气候怎样影响冷却选择?
Data-centre load drawn from TNB doubled in a year to 1,256 MW.从 TNB 取用的数据中心负荷一年翻倍至 1,256 MW。
Johor holds 67% of secured capacity.TNB 已锁定容量的 67% 在柔佛。
Sources checked 2026-10-15; climate from hourly observations 2020–2024来源核查 2026-10-15;气候来自 2020–2024 年逐时观测
PUE requirement or targetPUE 要求或目标
Design PUE target for hyperscale sites above 21.25 MW; recommended design WUE 2.2 m³/MWh21.25 MW 以上超大规模站点的设计 PUE 目标;建议设计 WUE 2.2 m³/MWh
WUE requirement or targetWUE 要求或目标
Recommended design WUE, in m³/MWh as the source states it (equal to L/kWh), working towards 2.0 over ten years; Johor sets no numeric WUE limit建议设计 WUE,单位按来源为 m³/MWh(等于 L/kWh),十年内向 2.0 推进;柔佛未设 WUE 数值上限
Power build-out电力建设规模
Data-centre maximum demand in TNB's secured pipeline, June 2026: 61 projects, 16 of them (2.21 GW) under construction2026 年 6 月 TNB 已锁定管线中的数据中心最大需求:61 个项目,其中 16 个(2.21 GW)在建
Biggest constraint最大约束
The biggest constraint is power: in Johor, TNB must review and approve the electricity supply before a data centre proceeds, and large centres are encouraged to sit within 100 m of transmission lines.最大约束是电力:在柔佛,数据中心须先经 TNB 审核批准供电才能推进,大型数据中心被鼓励建在输电线路 100 m 范围内。
| Month月份 | MW |
|---|---|
| 2025-06 | 603 |
| 2025-09 | 710 |
| 2025-12 | 850 |
| 2026-03 | 1,054 |
| 2026-06 | 1,256 |
TNB actual load utilisation of data centres; the source does not say whether this is IT or total loadTNB 统计的数据中心实际用电负荷;来源未说明是 IT 负荷还是总负荷
Thermal meaning热管理含义
Policy, efficiency, power and water政策、能效、电力与用水
Policies政策
- A Data Centre Task Force has existed since February 2025 as a joint platform of MITI and the Ministry of Digital.数据中心工作组自 2025 年 2 月起设立,是 MITI 与数字部的联合平台。 in force生效中 2025-02 source来源
- Johor's data-centre planning guidelines (April 2024) place data centres in industrial or commercial zones; a site outside these zones must seek guidance and approval from the state data-centre coordination committee (JPPPDNJ). The guidelines were approved by the state planning committee and executive council.柔佛数据中心规划指引(2024 年 4 月)将数据中心安排在工业或商业用地;位于这些用地之外的站点须向州数据中心发展协调委员会(JPPPDNJ)寻求指导并获得批准。指引经州规划委员会和州行政议会批准。 in force生效中 2024-04 source来源
Efficiency rules能效要求
- Design PUE targets: 1.4 and below for hyperscale above 21.25 MW at 132 kV or more; 1.6 for post-2020 colocation above 21.25 MW; 1.7 for smaller and older sites; to be validated once a baseline is set.设计 PUE 目标:132 kV 以上、21.25 MW 以上的超大规模 1.4 及以下;2020 年后的大型托管 1.6;较小或较旧的站点 1.7;基线建立后再验证。 condition of DESAC tax incentives (applications to 2027-12-31)DESAC 税收优惠条件(申请截至 2027-12-31) source来源
- Recommended design WUE is 2.2 m³/MWh or lower, working towards 2.0 over ten years; CUE must be declared, with no limit.建议设计 WUE 不高于 2.2 m³/MWh,十年内向 2.0 推进;CUE 须申报,无上限。 condition of DESAC tax incentivesDESAC 税收优惠条件 source来源
Power电力
- In Johor, TNB must review and approve the electricity supply before a data centre proceeds; large centres connect at 132–275 kV and are encouraged within 100 m of transmission lines or a main intake.柔佛规定数据中心开工前须经 TNB 审核批准供电;大型数据中心接入 132–275 kV,鼓励选址在输电线或主变电站 100 米内。 in force生效中 2024-04 source来源
- Corporate green-power buyers (CRESS) pay a system access charge of 20 sen/kWh for firm and 40 sen/kWh for non-firm supply, rates set for the 4th Regulatory Period after the July 2025 tariff schedule (announced 2025-08-29).企业绿电(CRESS)系统接入费为稳定供电 20 仙/千瓦时、非稳定供电 40 仙/千瓦时,为 2025 年 7 月新电价表之后第 4 监管期的费率(2025-08-29 公布)。 in force生效中 2025-08-29 source来源
Water水
- Johor requires water conservation in line with industry WUE practice and approval by the water operators, but sets no numeric WUE limit and no mandatory recycled water; it says centres should use direct-expansion or eco-chiller cooling and rainwater harvesting.柔佛要求按行业 WUE 做法节水并经供水部门批准,但没有 WUE 数值上限,也不强制用再生水;指引称应采用直膨或节能冷水系统以及雨水收集。 in force生效中 2024-04 source来源
- The national guideline says new sites should avoid water-stressed areas (water stress index below 0.8 in Peninsular Malaysia) and may use reclaimed water.国家指引称新址应避开缺水地区(马来半岛水压力指数低于 0.8),并可使用再生水。 condition of DESAC tax incentivesDESAC 税收优惠条件 2024-10 source来源
Projects项目
| Company公司 | Place地点 | As stated by the company公司表述 | Kind类型 | Source来源 |
|---|---|---|---|---|
| AirTrunk | Johor Bahru (JHB1) | 150 MW campus; initial phases over 50 MW (opened 2024-07-30)150 MW 园区;首期超过 50 MW(2024-07-30 开业) indirect evaporative cooling and direct-to-chip liquid cooling; design PUE 1.15间接蒸发冷却与芯片直接液冷;设计 PUE 1.15 | capacity容量 | link链接 |
| YTL Power with NVIDIA | Kulai, Johor | 600 MW green data-centre park (500 MW in 2023 releases); liquid-cooled GB200 NVL72 AI facility completed600 MW 绿色数据中心园区(2023 年发布为 500 MW);液冷 GB200 NVL72 AI 设施已建成 | capacity容量 | link链接 |
| DayOne | Johor (Nusajaya, Kempas) | 390 MW in the headline, over 478 MW in the body (not reconciled by the company)标题 390 MW,正文超过 478 MW(公司未说明差异) | capacity容量 | link链接 |
| Elmina Business Park, Selangor | USD 2 billion; water-cooled, about 10% less energy than air-cooled (company claim)20 亿美元;水冷,较风冷节能约 10%(公司说法) | investment投资 | link链接 | |
| AWS | not named未注明 | estimated USD 6.2 billion through 2038估计 2038 年前投资 62 亿美元 | investment投资 | link链接 |
| Microsoft | not named未注明 | USD 2.2 billion over four years (cloud, AI, skills, security)四年 22 亿美元(云、AI、技能、安全) | investment投资 | link链接 |
Capacity and investment are different measures and are never added. Capacities are the companies' own figures, with their qualifiers.容量和投资是不同的量,不相加。容量为公司自己的数字,保留其限定词。
What is not covered: 未覆盖:No official figure for IT MW in operation; TNB maximum demand and load are the best official numbers. No official climate normals for Senai or Kuala Lumpur were found; climate here comes from NOAA hourly observations. No data-centre tariff document or moratorium was found.没有官方的 IT MW 投运数字;TNB 的最大需求和负荷是最好的官方数字。未找到士乃或吉隆坡的官方气候常年值;本页气候来自 NOAA 逐时观测。未找到数据中心专用电价文件或暂停令。
Database view: every Malaysia number and fact on this page, with its source wording数据库视图:本页全部马来西亚数字和事实及来源原文52 rows52 行
| Field字段 | Fact事实 | Status状态 | Date日期 | Source wording来源原文 | Source来源 |
|---|---|---|---|---|---|
| Build scale建设规模 | Data-centre load drawn from TNB数据中心从 TNB 实际用电负荷: 2025-06, 603 MW | actual实际 | 2026-08-28 | Actual Load Utilisation 1,256MW for June 2026 | link链接 |
| Build scale建设规模 | Data-centre load drawn from TNB数据中心从 TNB 实际用电负荷: 2025-09, 710 MW | actual实际 | 2026-08-28 | Actual Load Utilisation 1,256MW for June 2026 | link链接 |
| Build scale建设规模 | Data-centre load drawn from TNB数据中心从 TNB 实际用电负荷: 2025-12, 850 MW | actual实际 | 2026-08-28 | Actual Load Utilisation 1,256MW for June 2026 | link链接 |
| Build scale建设规模 | Data-centre load drawn from TNB数据中心从 TNB 实际用电负荷: 2026-03, 1,054 MW | actual实际 | 2026-08-28 | Actual Load Utilisation 1,256MW for June 2026 | link链接 |
| Build scale建设规模 | Data-centre load drawn from TNB数据中心从 TNB 实际用电负荷: 2026-06, 1,256 MW | actual实际 | 2026-08-28 | Actual Load Utilisation 1,256MW for June 2026 | link链接 |
| Build scale建设规模 | TNB had 42 data-centre projects in its system with 5.65 GW of maximum demand, and a secured pipeline of 61 projects with 8.35 GW (16 under construction with 2.21 GW).TNB 系统内有 42 个数据中心项目,最大需求 5.65 GW;已锁定的项目共 61 个、8.35 GW(其中 16 个在建,2.21 GW)。 | actual and planned实际与计划 | 2026-06 | In System @ June 2026 42 projects @ 5.65GW … 16 projects … 61 projects … 2.21GW … 8.35GW Labels from one slide chart, in reading order; which count goes with which GW is read from the rendered chart.同一张幻灯片图表中的标签,按阅读顺序;项目数与 GW 的对应关系取自渲染后的图表。 | link链接 |
| Build scale建设规模 | Johor holds 67% of Malaysia's TNB-secured data-centre capacity: 29 of 61 projects, 5.6 of 8.3 GW.柔佛占马来西亚 TNB 锁定数据中心容量的 67%:61 个项目中的 29 个,8.3 GW 中的 5.6 GW。 | actual and planned实际与计划 | 2026-06 | Johor drives majority of Malaysia's secured DC capacity … 67% (5.6GW out of 8.3GW) of Malaysia's secured DC capacity Labels from one slide panel, in reading order.同一幻灯片版块中的标签,按阅读顺序。 | link链接 |
| Build scale建设规模 | MIDA recorded RM385.7 billion of data-centre-related investment from 2021 to the first half of 2026.MIDA 统计 2021 年至 2026 年上半年数据中心相关投资 3,857 亿令吉。 | actual (recorded investment)实际(已记录投资) | 2026 H1 | Malaysia has recorded RM385.7 billion in data-centre-related investments from 2021 to the first half of 2026 | link链接 |
| Power电力 | In Johor, TNB must review and approve the electricity supply before a data centre proceeds; large centres connect at 132–275 kV and are encouraged within 100 m of transmission lines or a main intake.柔佛规定数据中心开工前须经 TNB 审核批准供电;大型数据中心接入 132–275 kV,鼓励选址在输电线或主变电站 100 米内。 | in force生效中 | 2024-04 | Any requirements related to electricity supply must be reviewed and approved by Tenaga Nasional Berhad (TNB) before the data centre development proceeds. | link链接 |
| Power电力 | Corporate green-power buyers (CRESS) pay a system access charge of 20 sen/kWh for firm and 40 sen/kWh for non-firm supply, rates set for the 4th Regulatory Period after the July 2025 tariff schedule (announced 2025-08-29).企业绿电(CRESS)系统接入费为稳定供电 20 仙/千瓦时、非稳定供电 40 仙/千瓦时,为 2025 年 7 月新电价表之后第 4 监管期的费率(2025-08-29 公布)。 | in force生效中 | 2025-08-29 | the Government has set the SAC and CAC rates for the 4th Regulatory Period to be adjusted as follows | link链接 |
| Policies政策 | A Data Centre Task Force has existed since February 2025 as a joint platform of MITI and the Ministry of Digital.数据中心工作组自 2025 年 2 月起设立,是 MITI 与数字部的联合平台。 | in force生效中 | 2025-02 | established since February 2025 as a joint platform between MITI and the Ministry of Digital | link链接 |
| Water水 | Johor requires water conservation in line with industry WUE practice and approval by the water operators, but sets no numeric WUE limit and no mandatory recycled water; it says centres should use direct-expansion or eco-chiller cooling and rainwater harvesting.柔佛要求按行业 WUE 做法节水并经供水部门批准,但没有 WUE 数值上限,也不强制用再生水;指引称应采用直膨或节能冷水系统以及雨水收集。 | in force生效中 | 2024-04 | data centre development must incorporate water conservation strategies that align with industry-recognised standards for water usage effectiveness, as prescribed by the prevailing norms and best practices. | link链接 |
| Water水 | The national guideline says new sites should avoid water-stressed areas (water stress index below 0.8 in Peninsular Malaysia) and may use reclaimed water.国家指引称新址应避开缺水地区(马来半岛水压力指数低于 0.8),并可使用再生水。 | condition of DESAC tax incentivesDESAC 税收优惠条件 | 2024-10 | The organisation should avoid water stress areas in locating the new data centre by considering area with water stress index (WSI) of less than 0.8 | link链接 |
| Efficiency rules能效要求 | Design PUE targets: 1.4 and below for hyperscale above 21.25 MW at 132 kV or more; 1.6 for post-2020 colocation above 21.25 MW; 1.7 for smaller and older sites; to be validated once a baseline is set.设计 PUE 目标:132 kV 以上、21.25 MW 以上的超大规模 1.4 及以下;2020 年后的大型托管 1.6;较小或较旧的站点 1.7;基线建立后再验证。 | condition of DESAC tax incentives (applications to 2027-12-31)DESAC 税收优惠条件(申请截至 2027-12-31) | 1.4 and below (to be validated once baseline is established) | link链接 | |
| Efficiency rules能效要求 | Recommended design WUE is 2.2 m³/MWh or lower, working towards 2.0 over ten years; CUE must be declared, with no limit.建议设计 WUE 不高于 2.2 m³/MWh,十年内向 2.0 推进;CUE 须申报,无上限。 | condition of DESAC tax incentivesDESAC 税收优惠条件 | The recommended design WUE is 2.2 m3/MWh or lower | link链接 | |
| Policies政策 | Johor's data-centre planning guidelines (April 2024) place data centres in industrial or commercial zones; a site outside these zones must seek guidance and approval from the state data-centre coordination committee (JPPPDNJ). The guidelines were approved by the state planning committee and executive council.柔佛数据中心规划指引(2024 年 4 月)将数据中心安排在工业或商业用地;位于这些用地之外的站点须向州数据中心发展协调委员会(JPPPDNJ)寻求指导并获得批准。指引经州规划委员会和州行政议会批准。 | in force生效中 | 2024-04 | These Guidelines have been presented and approved by The State Planning Committee Meeting (SPC) No. 3/2023; and The Johor State Executive Council Meeting R.M No. 279/2024 … Buildings located outside commercial and industrial zones, including those in areas deemed unsuitable for data centre development, (e.g., adjacent to residential neighbourhoods), must seek guidance and secure approval from the Johor State Data Centre Development Coordination Committee (JPPPDNJ) | link链接 |
| Projects项目 | AirTrunk, Johor Bahru (JHB1): 150 MW campus; initial phases over 50 MW (opened 2024-07-30)150 MW 园区;首期超过 50 MW(2024-07-30 开业) (indirect evaporative cooling and direct-to-chip liquid cooling; design PUE 1.15间接蒸发冷却与芯片直接液冷;设计 PUE 1.15) | capacity容量 | 2024-07-30 | flagship Malaysian 150 megawatt (MW) hyperscale data centre in Johor Bahru … The initial phases of JHB1 will provide over 50MW of capacity | link链接 |
| Projects项目 | YTL Power with NVIDIA, Kulai, Johor: 600 MW green data-centre park (500 MW in 2023 releases); liquid-cooled GB200 NVL72 AI facility completed600 MW 绿色数据中心园区(2023 年发布为 500 MW);液冷 GB200 NVL72 AI 设施已建成 | capacity容量 | link链接 | ||
| Projects项目 | DayOne, Johor (Nusajaya, Kempas): 390 MW in the headline, over 478 MW in the body (not reconciled by the company)标题 390 MW,正文超过 478 MW(公司未说明差异) | capacity容量 | link链接 | ||
| Projects项目 | Google, Elmina Business Park, Selangor: USD 2 billion; water-cooled, about 10% less energy than air-cooled (company claim)20 亿美元;水冷,较风冷节能约 10%(公司说法) | investment投资 | link链接 | ||
| Projects项目 | AWS, not named未注明: estimated USD 6.2 billion through 2038估计 2038 年前投资 62 亿美元 | investment投资 | link链接 | ||
| Projects项目 | Microsoft, not named未注明: USD 2.2 billion over four years (cloud, AI, skills, security)四年 22 亿美元(云、AI、技能、安全) | investment投资 | link链接 | ||
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W20 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W20 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W25 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W25 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W25 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W32 at 5 K: 5,301 hours a year; single years 4,964–5,558; lowest-year coverage 96%、5 K:每年 5,301 小时;单年 4,964–5,558;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W32 at 10 K: 10 hours a year; single years 0–36; lowest-year coverage 96%、10 K:每年 10 小时;单年 0–36;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W32 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W40 at 5 K: 8,756 hours a year; single years 8,752–8,760; lowest-year coverage 96%、5 K:每年 8,756 小时;单年 8,752–8,760;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W40 at 10 K: 7,123 hours a year; single years 6,918–7,277; lowest-year coverage 96%、10 K:每年 7,123 小时;单年 6,918–7,277;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W40 at 15 K: 2,799 hours a year; single years 1,919–3,393; lowest-year coverage 96%、15 K:每年 2,799 小时;单年 1,919–3,393;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W45 at 5 K: 8,760 hours a year; single years 8,760–8,760; lowest-year coverage 96%、5 K:每年 8,760 小时;单年 8,760–8,760;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W45 at 10 K: 8,756 hours a year; single years 8,752–8,760; lowest-year coverage 96%、10 K:每年 8,756 小时;单年 8,752–8,760;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Johor (Senai)柔佛(士乃) (48679099999), W45 at 15 K: 7,123 hours a year; single years 6,918–7,277; lowest-year coverage 96%、15 K:每年 7,123 小时;单年 6,918–7,277;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W20 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W20 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W25 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W25 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W25 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W32 at 5 K: 4,174 hours a year; single years 3,710–4,459; lowest-year coverage 96%、5 K:每年 4,174 小时;单年 3,710–4,459;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W32 at 10 K: 1 hours a year; single years 0–2; lowest-year coverage 96%、10 K:每年 1 小时;单年 0–2;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W32 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W40 at 5 K: 8,746 hours a year; single years 8,728–8,757; lowest-year coverage 96%、5 K:每年 8,746 小时;单年 8,728–8,757;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W40 at 10 K: 6,523 hours a year; single years 6,327–6,720; lowest-year coverage 96%、10 K:每年 6,523 小时;单年 6,327–6,720;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W40 at 15 K: 1,278 hours a year; single years 711–1,718; lowest-year coverage 96%、15 K:每年 1,278 小时;单年 711–1,718;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W45 at 5 K: 8,760 hours a year; single years 8,760–8,760; lowest-year coverage 96%、5 K:每年 8,760 小时;单年 8,760–8,760;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W45 at 10 K: 8,746 hours a year; single years 8,728–8,757; lowest-year coverage 96%、10 K:每年 8,746 小时;单年 8,728–8,757;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA | |
| Climate气候 | Kuala Lumpur (Subang)吉隆坡(梳邦) (48647099999), W45 at 15 K: 6,523 hours a year; single years 6,327–6,720; lowest-year coverage 96%、15 K:每年 6,523 小时;单年 6,327–6,720;最低单年覆盖率 96% | computed by this site本站计算 | 2020–2024 | NOAA |